Project overview*

EIS status Approved with conditions
Description A 373,662-megalitre dam, water from which will be transported via a 133 km pipeline to Moranbah and will primarily service coal mines (and associated communities) in Central Queensland's coal basins.
Proponent SunWater Ltd (a government-owned corporation)
Location/s
  • Dam: on Connors River near Mount Bridgett, 110 km east of Moranbah and 70 km south of Sarina
  • Pipeline: will run from the dam to Moranbah
Map
Local government/s Isaac Regional Council
Key features
  • roller-compacted concrete dam, including a central spillway and aquatic fauna transfer device
  • pipeline
  • associated infrastructure
  • recreational area beside water storage area
  • upgrade of access roads
  • commissioning of temporary resource extraction areas

*Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

Date Activity
30 June 2017 The Coordinator-General extended the currency period for the EIS Evaluation Report from 3 July 2017 to 3 July 2019.
16 December 2015 The Coordinator-General extended the currency period for the EIS Evaluation Report from 20 January 2016 to 3 July 2017.
19 April 2012 Commonwealth Minister for the Environment's approval of 'controlled action', subject to conditions. More information
20 January 2012 Coordinator-General's report on EIS released.
14 March 2011
6 February 2010 to
22 March 2010
Public consultation on EIS.
16 July 2009 Terms of reference for EIS (PDF icon 319 KB) released.
31 January 2009 to
9 March 2009
Public consultation on draft terms of reference for EIS.
25 September 2008 Project deemed a controlled action by Commonwealth Minister for the Environment. More information
28 August 2008 Project referred to Commonwealth Minister for the Environment.
7 March 2008 Gazettal of 'significant project' declaration (PDF icon 182 KB)
20 February 2008 Application, including initial advice statement (PDF icon 534 KB), submitted.

Read more about the EIS process.

Australian Government approval

Commonwealth Minister for the Environment's approval of controlled action, subject to conditions.