Project overview*
| EIS status | EIS active |
| Description | 224 kilometre single-track dual-gauge freight railway |
| Proponent | Australian Rail Track Corporation Limited |
| Location/s | Queensland Border to Gowrie. Map |
| Local government/s |
|
| Investment | $1.4 billion |
| Key features |
|
| Expected completion | 2025 |
| Jobs |
|
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| Currently | Draft EIS being prepared by proponent |
| 16 November 2018 | Terms of reference for EIS ( |
| 7 May - 18 June 2018 | Draft Terms of reference for EIS public consultation ( |
| 9 April 2018 | Delegate for the Commonwealth Minister for the Environment and Energy decided that the project is a 'controlled action' |
| 16 March 2018 | Gazettal ( |
| 2 March 2018 |
Complete final initial advice statement ( The above has also been split into smaller documents for easier downloading:
|
| 16 February 2018 | Application, including initial advice statement submitted. |
| 16 February 2018 | Project referred to Commonwealth Minister for the Environment and Energy. |