Biloela CBD Drainage Improvements
- Council: Banana Shire Council
- Fund: Royalties for Resource Producing Communities Fund
- Category: Flood Mitigation Infrastructure
- Round: 2
Flood immunity will be improved for local businesses and homes with an upgrade to Biloela’s stormwater network.
Council will now install the necessary infrastructure to increase capacity of the CBD drainage system, alleviating overloading of the system during moderate and severe rain which has previously created road safety concerns and inundation of properties located in Kariboe, Callide and Melton Streets.
Funding
- Total project cost$1,420,000
- Funding (BoR)$690,000
- Funding (Council)$730,000
Jobs*
- Jobs4.4
Construction
- Current stageConstruction underway
- Construction startApril 2017
- Expected completionNovember 2017
* Average number of Full-Time Equivalent (FTE) jobs supported by project construction (based on Queensland Treasury's Guidelines for estimating FTE jobs directly supported by the capital works program).
Disclaimer: Information on this page may change over the life of the project. Funding amounts referenced are as approved.