Project changes
Since the publication of the Coordinator-General's report on the EIS, Australia Pacific LNG has applied for the following changes to the Australia Pacific LNG Project.
Project change application 7 – Gas fields -workers accommodation
Date | Activity |
---|---|
3 February 2020 | Change application withdrawn by Coordinator-General. |
19 December 2019 | Request for withdrawal of change application. |
26 October 2018 to 14 December 2018 | Public consultation on change application. |
11 June 2018 | Proponent's change application ( 18.6 MB) submitted. |
Project change application 6 – Imposed Conditions (General)
Date | Activity |
---|---|
21 June 2016 | Coordinator-General’s report on project change ( 824 KB). |
13 May 2016 | Proponent's project change application ( 9 MB) submitted. |
Project change application 5 – Social
Date | Activity |
---|---|
29 September 2015 | Coordinator-General's report on project change ( 5.2 MB) released, approving the change. |
16 September 2015 | Proponent's project change application ( 6.5 MB) submitted. |
Project change application 4 – General Audit and LNG Facility Operational Environmental Management Plan
Date | Activity |
---|---|
28 October 2014 | Coordinator-General's report on project change ( 737 KB) released, approving the change. |
2 October 2014 | Proponent's project change application ( 1.7 MB) submitted. |
Project change application 3 – CSG Industry Monitoring Group
Date | Activity |
---|---|
29 October 2013 | Coordinator-General's report on project change ( 801 KB) released, approving the change. |
18 September 2013 | Proponent's project change application ( 517 KB) submitted. |
Project change application 2 – Alignment of reporting conditions to SIA Guidelines
Date | Activity |
---|---|
29 October 2013 | Coordinator-General's report on project change ( 803 MB) released, approving the change. |
18 September 2013 | Proponent's project change application ( 121 KB) submitted. |
Project change application 1 - Local content strategy
Date | Activity |
---|---|
27 March 2013 | Coordinator-General's report on project change ( 1.04 MB) released, approving the change. |
25 March 2013 | Proponent's project change application ( 380 KB) submitted. |
Last updated: 16 Mar 2023