Project changes

Since the publication of the Coordinator-General's report on the EIS, Australia Pacific LNG has applied for the following changes to the Australia Pacific LNG Project.

Project change application 7 – Gas fields -workers accommodation

DateActivity
3 February 2020 Change application withdrawn by Coordinator-General.
19 December 2019 Request for withdrawal of change application.
26 October 2018 to 14 December 2018 Public consultation on change application.
11 June 2018 Proponent's change application (PDF icon 18.6 MB) submitted.

Project change application 6 – Imposed Conditions (General)

DateActivity
21 June 2016 Coordinator-General’s report on project change (PDF icon 824 KB).
13 May 2016 Proponent's project change application (PDF icon 9 MB) submitted.

Project change application 5 – Social

DateActivity
29 September 2015 Coordinator-General's report on project change (PDF icon 5.2 MB) released, approving the change.
16 September 2015 Proponent's project change application (PDF icon 6.5 MB) submitted.

Project change application 4 – General Audit and LNG Facility Operational Environmental Management Plan

DateActivity
28 October 2014 Coordinator-General's report on project change (PDF icon 737 KB) released, approving the change.
2 October 2014 Proponent's project change application (PDF icon 1.7 MB) submitted.

Project change application 3 – CSG Industry Monitoring Group

DateActivity
29 October 2013 Coordinator-General's report on project change (PDF icon 801 KB) released, approving the change.
18 September 2013 Proponent's project change application (PDF icon 517 KB) submitted.

Project change application 2 – Alignment of reporting conditions to SIA Guidelines

DateActivity
29 October 2013 Coordinator-General's report on project change (PDF icon 803 MB) released, approving the change.
18 September 2013 Proponent's project change application (PDF icon 121 KB) submitted.

Project change application 1 - Local content strategy

DateActivity
27 March 2013 Coordinator-General's report on project change (PDF icon 1.04 MB) released, approving the change.
25 March 2013 Proponent's project change application (PDF icon 380 KB) submitted.

Read more about project changes.