Project changes

Since the publication of the Coordinator-General's report on the EIS, BHP Billiton Mitsubishi Alliance (BMA) has applied for the following changes to the Caval Ridge Mine project.

Read more about project changes.

Project change application 10 – Audit condition changes

http://www.statedevelopment.qld.gov.au/assessments-and-approvals/caval-ridge-mine-project-changes.html
Date Activity
26 May 2014 Coordinator-General's report on project change (PDF icon 390 KB) released, approving the change.
3 April 2014 Proponent's project change application (PDF icon 1.9 MB) submitted.

Project change application 9 – Housing and accommodation condition changes

Date Activity
27 September 2013 Coordinator-General's report on project change (PDF icon 845 KB) released, approving the change.
16 August 2013 Proponent's project change application (PDF icon 8.3 MB) submitted.

Project change application 8 – Accommodation village condition changes

Date Activity
2 September 2013 Coordinator-General's report on project change (PDF icon 6.6 MB) released, approving the change.
21 June 2013 to
1 August 2013
Public consultation on project change application.
31 May 2013 Proponent's project change application (PDF icon 5.3 MB) submitted.

Project change application 7 - Local buying program

Date Activity
27 March 2013 Coordinator-General's report on project change (PDF icon 828 KB) released, approving the change.
22 March 2013 Proponent's project change application (PDF icon 230 KB) submitted.

Project change application 6 - Miscellaneous condition amendments

Date Activity
28 March 2013 Coordinator-General's report on project change (PDF icon 550 KB) released, approving the change.
25 February 2013 Proponent's project change application (PDF icon 510 KB) submitted.

Project change application 5 - Rail alignment

Date Activity
3 April 2012 Coordinator-General's report on project change (PDF icon 440 KB) released, approving the change.
20 October 2011 Proponent's project change application (PDF icon 4.51 MB) submitted.

Project change application 4 - 100 per cent fly-in/fly-out operational workforce

Date Activity
2 September 2011 Coordinator-General's report on project change (PDF icon 213 KB) released, approving the change.
18 July 2011 to
15 August 2011
Public consultation on project change application.
15 June 2011 Proponent's project change application (PDF icon 2.16 MB) submitted.

Project change application 3 - Housing study

Date Activity
14 July 2011 Coordinator-General's report on project change (PDF icon 614 KB) released, approving the change.
3 June 2011 Proponent's project change application (PDF icon 608 KB) submitted.

Project change application 2 - Administration of environmental authority

Date Activity
16 November 2010 Coordinator-General's report on project change (PDF icon 124 KB) released, approving the change.
9 November 2010 Proponent's project change application submitted. It comprises two documents:

Project change application 1 - Accommodation village location and capacity

Date Activity
17 February 2011 Coordinator-General's report on project change (PDF icon 608 KB) released, approving the change.
16 November 2010 to
15 November 2010
Public consultation on proponent's project change application.
29 September 2010 Proponents project change application submitted. It comprises three documents: