Project changes
Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Gladstone LNG Project.
Read more about project changes.
Project change application 6 – Gas field disturbance
Date | Activity |
---|---|
8 August 2019 | Coordinator-General’s amendment report ( 79 KB) released, correcting a clerical error identified in the change report dated 21 March 2018. |
21 March 2018 | Coordinator-General's report on project change ( 5 MB) released, approving the change (as amended 8 August 2019). |
16 September 2016 | Proponent's project change application ( 12 MB) submitted. |
Project change application 5 – Social
Date | Activity |
---|---|
13 May 2015 | Coordinator-General's report on project change ( 706 KB) released, approving the change. |
23 January 2015 | Proponent's project change application ( 923 KB) submitted. |
Project change application 4 – Liquefied Natural Gas (LNG) Train 3
Date | Activity |
---|---|
14 May 2014 | Coordinator-General's report on project change ( 170 KB) released, approving the change. |
28 May 2014 | Proponent's project change application ( 471 KB) submitted. |
Project change application 3 – audit conditions
Date | Activity |
---|---|
9 March 2014 | Coordinator-General's report on project change ( 838 KB) released, approving the change. |
3 January 2014 | Proponent's project change application ( 728 KB) submitted. |
Project change application 2 – Increase in pipe transport
Date | Activity |
---|---|
5 November 2013 | Coordinator-General's report on project change ( 136 KB) released, approving the change. |
9 October 2013 | Proponent's project change application ( 2.14 MB) submitted. |
Project change application 1 - Local industry participation plan
Date | Activity |
---|---|
27 March 2013 | Coordinator-General's report on project change ( 743 KB) released, approving the change. |
19 March 2013 | Proponent's project change application ( 70 KB) submitted. |
Last updated: 16 Mar 2023