Kidston Pumped Storage Hydro Project
Project overview*
IAR status | Approved with conditions |
Description | A 250-megawatt pumped storage hydroelectric power generation facility – the beneficial use of the decommissioned Kidston Gold Mine’s upper and lower pits. |
Proponent | Genex Power Limited |
Location/s | Kidston, Queensland approximately 280 km north-west of Townsville. Map |
Local government/s | Etheridge Shire Council |
Investment | $777 million |
Key features | The project would act as a natural battery storage, allowing energy to be stored and harnessed on demand and includes the following components:
|
Expected completion | 2025 |
Jobs |
|
IAR process
Date | Activity |
---|---|
27 April 2021 | Coordinator-General’s report on project change ( 145 KB) released. |
24 September 2019 | Coordinator-General correspondence to Genex Power Limited ( 306 KB). |
22 May 2019 | Coordinator-General correspondence to Genex Power Limited ( 230 KB). |
5 April 2019 | Coordinator-General’s report on the IAR ( 2.4 MB) release. |
28 March 2019 | The Coordinator-General accepted the draft IAR as the final IAR. Impact assessment report ( 28 MB), submitted. Supplementary information to the IAR ( 5.3 MB), submitted. IAR sections, submitted:
|
25 March 2019 | The Coordinator-General accepted the draft IAR as the final IAR. The evaluation stage has commenced. |
11 January 2019 | The proponent lodged a draft IAR. |
28 September 2018 | Gazettal ( 250 KB) of 'coordinated project' declaration. |
28 September 2018 | Application, including initial advice statement submitted. |
Read more about the IAR process.
* Project information supplied by proponent and subject to change.
Last updated: 06 Aug 2024