Project changes

Since the publication on the Coordinator-General's report on the EIS, QGC has applied for the following changes to the Queensland Curtis LNG Project.

Read more about project changes.

Project change application 8 - Social

Date Activity
14 May 2015 Coordinator-General's report on project change (PDF icon 661 KB) released, approving the change.
2 April 2015 Proponent's project change application (PDF icon 413 KB) submitted.

Project change application 7 - Third Train condition

Date Activity
14 July 2014 Coordinator-General's report on project change (PDF icon 202 KB) released, approving the change.
13 June 2014 Proponent's project change application (PDF icon 827 KB) submitted.

Project change application 6 - CSG Industry Monitoring Group condition

Date Activity
02 June 2014 Coordinator-General's report on project change (PDF icon 578 KB) released, approving the change.
19 May 2014 Proponent's project change application (PDF icon 1.2 MB) submitted.

Project change application 5 - Social reporting conditions

Date Activity
25 February 2014 Coordinator-General's report on project change (PDF icon 1.8 MB) released, approving the change.
7 February 2014 Proponent's project change application (PDF icon 482 KB) submitted.

Project change application 4 - Social impact management plan (SIMP) reporting and auditing arrangements

Date Activity
5 November 2013 Coordinator-General's report on project change (PDF icon 261 KB) released, approving the change.
18 October 2013 Proponent's project change application (PDF icon 97 KB) submitted.

Project change application 3 - Housing conditions

Date Activity
6 September 2013 Coordinator-General's report on project change (PDF icon 719 KB) released, approving the change.
9 August 2013 Proponent's project change application (PDF icon 1.5 MB) submitted.

Project change application 2 - Local Industry Participation Plan

Date Activity
27 March 2013 Coordinator-General's report on project change (PDF icon 732 KB) released, approving the change.
18 March 2013 Proponent's project change application (PDF icon 972 KB) submitted.

Project change application 1 - Pipeline transport

Date Activity
21 September 2011 Coordinator-General's report on project change (PDF icon 1.13 MB) released, approving the change.
24 June 2011 Proponent's project change application (PDF icon 1.93 MB) submitted.