Since the publication of the Coordinator-General's report on the EIS, Shute Harbour Marina Pty Ltd has applied for the following changes to the Shute Harbour Marina project.

Project change application 1 - Development approvals

DateActivity
21 December 2018 Coordinator-General's report on project change (PDF icon 171 KB) released, approving the change.
14 December 2018 Proponent's project change application (PDF icon 112 KB) submitted.