Project changes - South of the Embley (Amrun)
Since the publication of the Coordinator-General's report on the EIS, RTA Weipa Pty Ltd has applied for the following changes to the South of the Embley (Amrun) project.
Project change application 4 – Accommodation term and location
Date | Activity |
---|---|
3 November 2015 | Coordinator-General's report on project change ( 197.0 MB) released, approving the change. |
14 October 2015 to 28 October 2015 | Project change application ( 8.8 MB) public consultation. |
28 September 2015 | Proponent's project change application submitted. |
Project change application 3 – Infrastructure facilities and volume and disposal of dredge spoil
Date | Activity |
---|---|
18 September 2015 | Coordinator-General's report on project change ( 193 KB) released, approving the change. |
15 September 2015 | Proponent's project change application ( 157 KB) submitted. |
Project change application 2 – General conditions
Date | Activity |
---|---|
21 November 2013 | Coordinator-General's report on project change ( 813 KB) released, approving the change. |
30 August 2013 | Proponent's project change application ( 4.85 MB) submitted. |
Project change application 1 - Social conditions
Date | Activity |
---|---|
1 October 2013 | Coordinator-General's report on project change ( 591 KB) released, approving the change. |
30 August 2013 | Proponent's project change application ( 4.1 MB) submitted. |
Last updated: 16 Mar 2023