The Department of State Development and Infrastructure is changing to the Department of State Development, Infrastructure and Planning. Work is underway to update this website. Read more about the new Ministerial portfolios. For Planning-related matters, please visit planning.qld.gov.au

Skip to content

Galilee Basin Power Station

Project overview*

EIS status EIS active
Description A 900-megawatt (MW) coal-fired power station incorporating clean-coal low-emission technology and carbon capture and storage.
Proponent Galilee Power Pty Ltd (a subsidiary of Waratah Coal Pty Ltd)
Location/s 30 km north-west of Alpha, in central Queensland. Map
Local government/s Barcaldine Regional Council
Key features
  • power station (2 x 450 MW modules, with construction of the second dependent on demand)
  • geosequestration of CO2 in western Galilee Basin

* Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

Date Activity
13 April 2015 'Coordinated project' declaration lapsed.
16 September 2014 Coordinator-General stated a new project declaration lapse date of 13 April 2015.
9 April 2013 Final terms of reference (PDF icon 310 KB) issued.
12 January 2013 to
22 February 2013
Draft terms of reference for EIS public consultation.
11 September 2009 Gazettal of 'coordinated project' declaration (PDF icon 208 KB)
9 June 2009 Application, including initial advice statement (PDF icon 1.83 MB), submitted.

Read more about the EIS process.

Last updated: 09 Nov 2021