Six Mile Creek Dam Safety Upgrade project
Project overview*
Status | Approved with conditions |
Description | Proposal to upgrade the Six Mile Creek Dam to meet modern safety standards |
Proponent | Seqwater (Queensland Bulk Water Supply Authority) |
Location/s | Lake Macdonald, approximately 4km from Cooroy in Noosa Shire Map |
Local government/s | Noosa Shire Council |
Investment | $100 million |
Key features |
|
Expected completion | 2026 |
Jobs | Up to 110 (construction) |
Project changes
Since the publication of the Coordinator-General’s report on the impact assessment report (IAR) in 2019, the proponent has applied for changes to the Six Mile Creek Dam Safety Upgrade project.
Read more about the project changes.
IAR process
Date | Activity |
---|---|
15 May 2023 | Coordinator-General stated a new lapse date for the Coordinator-General’s IAR evaluation report of 20 May 2025. |
7 November 2019 | Australian Minister for the Environment’s approval of ‘controlled action’ subject to conditions. |
20 May 2019 | Coordinator-General’s report on final IAR ( 6.6 MB) released. |
30 April 2019 | The Coordinator-General accepted the draft IAR as the final IAR. Impact assessment report submitted. |
11 February 2019 to 11 March 2019 | Draft IAR public consultation. |
22 December 2017 | Gazettal ( 250 KB) of ‘coordinated project’ declaration. |
6 December 2017 | Australian Minister for the Environment and Energy decided the project is a ‘controlled action’. |
18 October 2017 | Project referred to the Australian Minister for the Environment and Energy. |
15 September 2017 | Application, including initial advice statement ( 3.2 MB), submitted. |
Read more about the IAR process.
* Project information supplied by proponent and subject to change.
Last updated: 29 Jan 2025